(The Center Square) – King County could avoid a round of permit fee increases in 2027 as the division figures out how to fix its funding model to address a $10.9 million accumulated negative fund balance.

The King County Department of Local Services’ Permitting Division has ended every year since at least 2017 with a negative balance in the Permit Fund. The account first showed a negative cash balance in 2025, with it reaching $2.49 million in the red by the end of September, according to county reporting.

The office relies on interfund loans to keep things running, with the “average amount borrowed” listed as $2.47 million in September. King County officials reviewed the executive’s plan to eliminate the deficit during a committee meeting on Wednesday.

“I hate to see those kinds of dramatic increases,” Councilmember Reagan Dunn said while chairing his Local Services and Land Use Committee, referring to fees that have increased nearly 67% since 2024.

King County Executive Girmay Zahilay submitted a plan that relies on inflation-linked permit fee hikes, additional general fund support across 2028-29 and spending $1 million less than budgeted every two years to curb the permit fund’s deficit; the committee recommended a substitute with minor changes.

Zahilay’s plan included an ordinance that would increase some fees and lower others to align with the amount of work it takes. The report included two paths, describing the first as a “general fund bailout.”

One option would increase fees by 11% to 14%, followed by inflation-adjusted fee increases of 6% to 8% every two years, with $5 million to $5.4 million in one-time general fund support.

The other option would maintain current fee rates before future inflation-adjusted increases, with $2.1 million to $2.8 million in ongoing general fund support. Both plans assume it will take four years to balance the fund.

The report says Zahilay doesn’t recommend either quite yet, but plans to review them again next year.

“We had a general fund component to assist us with some of that work,” Permitting Division Director Liz Stead said Wednesday, regarding how Bellevue’s funding model worked when she was at the city.

“That helped us sustain our rates and not have such high rates that we were impinging development, but we were also able to provide services,” she said, explaining that Bellevue supported the permitting office with its general fund for work that benefits the community but can’t be billed to specific permits.

The Budget and Fiscal Management Committee advanced a substitute fee ordinance Monday to extend existing rates through 2027, including a temporary 3.5% technology surcharge.

On Wednesday, Dunn and his committee separately recommended Zahilay’s plan to the council after making minor changes.

Permit fees accounted for 94% of the division’s revenue in 2026, so when applications fall, the office’s ability to function does too. Salaries and benefits, as with many governments, make up over two-thirds of the division’s costs in the 2026-27 budget, and cutting headcount could also affect permitting operations.

Last month, an audit found the division hadn’t formally documented what it needs to replace its aging system, even though applicants pay a 3.5% technology surcharge.

Zahilay’s recovery plan extends the surcharge in hopes of establishing a single “unified permitting platform” for “a better user experience.”

“I don’t want us to be the culture of no, the gatekeepers,” Stead said about her vision for the division.